Project Timeline

DESCRIPTION OF WORKDATE*
Town Council Authorization to contract EIR/Design consultantsJan. 6, 2016
Notice to proceedJan. 11, 2016
AlternativesJan. 22, 2016
Public input on alternatives: 4-6pm, Suite Z (Minaret Village Mall)Jan. 29, 2016
Alternative selectionFeb. 2016
Preliminary designMar. 2016
EIR meeting & public input on preliminary design: 4-6pm, Suite. ZMar. 18, 2016
Presentation to design review committee & Planning/Economic Dev. CommissionApril 13, 2016
Town Council presentationMay 4, 2016
Notice of Preparation/Scoping public review periodJune 2-July 1, 2016
EIR scoping meeting with Planning and Economic Development Commission, 2pmJune 8, 2016
Preparation of Draft EIRJuly-Sept., 2016
Public review of Draft EIROct.-Nov., 2016
Preparation of Final EIRJanuary, 2017
Recreation Commission and Mammoth Lakes Recreation consider funding optionsMay 2, 2017
Public Hearing and EIR certification by PDECMay 10, 2017
Town Council considers certification of EIRMay 17, 2017
Town Council considers funding certification & direction to proceed with projectMay 17, 2017
Authorize final construction documentsJune, 2017
Town Council award partial grading and utilities workAugust, 2017
Town Council award contract for roof structureJanuary, 2018
Town Council award contract for buildings, ice rink and site workApril, 2018
Begin constructionMay, 2018
Ribbon CuttingHalloween 2018
* Schedule subject to change